TBM Launching in September of 2018

2018-10-08

Product No.

TypeUserProjectDistance of trial tunneling(m)

Beginning time of assembly

Beginning time of commissioning 

Beginning time of trial tunneling

DH501
ZTE6880 (EPB with a diameter of 6880mm)China Construction Tunnel Corp., Ltd.Chongqing Metro
300
2018-7-52018-8-24
2018-9-1
DZ418ZTE8800 (EPB with a diameter of 8800mm)China Railway 19 Bureau Group Co., Ltd.Guangzhou Metro
200
2018-7-25
2018-8-14
2018-9-5
DZ400

ZTE6250 (EPB with a diameter of 6250mm)

China Railway 16th Bureau Group Co., Ltd.Moscow Metro
200
2018-5-12
2018-9-3
2018-9-7
DZ476

ZTE6410 (EPB with a diameter of 6410mm)

China Railway 11th Bureau Group

Luoyang Metro
300
2018-8-31
2018-9-12
2018-9-17
DH241
ZTE6410 (EPB with a diameter of 6410mm)

Taiyuan Heavy Industry Co., Ltd.

Taiyuan Metro
200
2018-7-5
2018-9-7
2018-9-18
DZ468
ZTE6410 (EPB with a diameter of 6410mm)China Railway 16th Bureau Group Co., Ltd.Luoyang Metro300
2018-9-8
2018-9-20
2018-9-26